Tanks East zeit Petroleum Company
2011-04-22 To 2011-04-22

Project of complete maintenance works for three oil storage tanks TK#220 A\B\C for east zeit Petroleum Company.

The works include repainting works for all the tanks body, making any welding works needed in the bottom, shell and roof

We make complete replacing for the fire fighting system and the cooling system